Solid Waste Management Project
Components
  • Rehabilitation of old landfill
  • Construction of MBT plant
  • Introduction of new SWM system
Financing

Phase I

  • €20 million EBRD loan
  • €5 million EBRD loan – Clean Technology Fund
  • €10 million Grant of the Eastern Europe Energy Efficient Partnership Foundation
  • €6,75 million from city budget

Phase II

  • EIB loan
Phase I components
Components €, mln.
Rehabilitation of Hrybovychi landfill: Phase 1 11,56
Installation of leachate treatment facilities at Hrybovychi landfill 1,8
Construction of waste mechanical and biological treatment facilities: Phase 1 23,5
Development of the household civic amenity centers 4,14
Locally co-financed capex (technical design, preparatory construction works for MBT) 1,75
Total 41,75
MBT Plant

Mechanical sorting

  • Pre-sorting
  • Screening
    • Separate finer fraction for composting
  • Manual sorting on coarser fraction
  • Baling of separated recyclables and residual

Composting

  • Windrow (covered) or tunnel system
  • Post-composting:
    • Removal of metals
    • Screening to separate fine fraction
    • Coarse fraction divided into inerts or RDF
  • Air filtration system

RDF production

  • High-quality RDF separated mechanically from light fraction of residual waste after hand-sorting and then shredded
  • Low quality RDF from coarse fraction post-composting

Sorting line

  • Mechanical sorting of separately collected waste
  • Separation of:
    • Cardboard
    • Paper
    • Plastics
      • PET
      • PP
      • PE
    • Tetrapaks

250 000 tons / year – mass balance:

MBT Plant

  • 5% recyclables
  • 10% compost
  • 30% RDF
  • 20% inert waste

Landfill

  • 35% residual waste

€25 – 30 gate fee

Project manager

LMC Zelene Misto
+38 032 297 55 70
zelene.misto@lvivcity.gov.ua
www.zelenemisto.info

Lviv Investment Office Lviv City Council
79006, Ukraine, Lviv Rynok sq. 1

+38 032 254 60 06
invest@lvivcity.gov.ua